HIGHLIGHTS
- Positive formal construction decision on the Cariboo Gold Project made by the Board of Directors, with an expected first gold pour in Q1 2029 and commercial production in H2 2029
- US$30 million strategic private placement from an affiliate of Trafigura, concentrate and doré off-take from Trafigura, and potential prepayment facility of up to US$120 million
- Go-forward capital obligation update for the Cariboo Gold Project of $990 million, supported by total available and proposed estimated sources of capital of up to $1,637 million, including $837 million in cash & equivalents
- Project completion estimated at 22% as of July 31, 2026; Detailed engineering is approximately 40% complete; Procurement and commitments for long-lead items is progressing with an overall completion of approximately 44%; $325 million has been committed to date
Article contentWe apologize, but this video has failed to load.Try refreshing your browser, or
tap here to see other videos from our team.Article content
Story continues below
This advertisement has not loaded yet, but your article continues below.
Article content
TORONTO, Sept. 14, 2026 (GLOBE NEWSWIRE) — Osisko Gold Group Inc. (NYSE: OGG, TSXV: OGG) (“Osisko Gold” or the “Company“) is pleased to announce that its Board of Directors has made a formal positive decision to proceed with the construction of the Company’s 100%-owned Cariboo Gold Project (“Cariboo” or the “Project“), located in central British Columbia, Canada.
Article contentArticle content
Sean Roosen, Chairman and CEO, commented: “The Board’s formal positive decision to commence full-scale construction of our flagship Cariboo Gold Project represents a defining milestone for Osisko Gold and a pivotal inflection point toward our objective of becoming an intermediate gold producer. This decision is a culmination of more than a decade of de-risking work on the Project, from early exploration when the first drills hit the ground in 2015, through permitting and technical studies, and into project financing and pre-construction. It reflects our confidence in the significant long-term value Cariboo can deliver to our shareholders and other stakeholders, and in the transformational impact it can have on the future of Osisko Gold. I’d like to commend our talented team for their professionalism, dedication and extensive contributions over the years that have brought us to this important milestone.”
Article content
Story continues below
This advertisement has not loaded yet, but your article continues below.
Article content
“With this step forward, supported by our strong balance sheet position and other sources of available and proposed funding, our focus is now firmly on disciplined project execution toward first gold in early 2029. Based on an estimated remaining go-forward capital obligation of C$990 million and spot gold prices of US$4,350/oz, the Project demonstrates robust economics with after-tax NPV5% of C$3.2 billion, after-tax IRR of 42.7%, and average annual free cash flow of C$642 million in the first 5 years, underscoring its significant leverage to the gold price. Construction is expected to support 613 direct jobs at its peak, followed by 525 permanent jobs during operations, while generating substantial direct and indirect economic benefits for local communities and the Province of British Columbia. Bringing Cariboo through construction and into production represents only the first step in establishing a strong platform for the Company’s long-term growth strategy. In parallel, we continue to accelerate ongoing conversion drilling within the current deposit and advance exploration of the substantial potential at depth and along strike within the existing permit footprint, as well as across the broader Cariboo regional property. We look forward to providing further regular updates on our progress.”