This section is The content in this section is supplied by GlobeNewswire for the purposes of distributing press releases on behalf of its clients. Postmedia has not reviewed the content. by GlobeNewswire Article content

Mining Operations Underway and 11 Tonnes of Concentrate Shipped to São Paulo

Sign In or Create an Account

or View more offersArticle content

VANCOUVER, British Columbia, Sept. 15, 2026 (GLOBE NEWSWIRE) — JZR Gold Inc. (TSXV: JZR) (OTCPK: JZRIF) (the “Company” or “JZR”) is pleased to provide an operational update on the Vila Nova Gold Project (the “Project”) located in Amapá State, Brazil, following the Company’s assumption of operatorship on May 28, 2026.

Article contentWe apologize, but this video has failed to load.Try refreshing your browser, or
tap here to see other videos from our team.Article content

Since assuming operatorship, JZR has been focused on transitioning the Project into a stable and consistently operating processing operation. This transition has involved several important steps, including securing a mining contractor, mobilizing the necessary equipment to site, recruiting and training plant operators, and assembling an operating team capable of managing the Project.

Article content

Story continues below

This advertisement has not loaded yet, but your article continues below.

Article content

Mining Contractor Mobilized and Operations Established

Article contentArticle content

Following the assumption of operatorship, the Company required time to identify and secure an appropriate mining contractor, finalize a contract and mobilize the contractor and its equipment to the Project site. RR Bueno, JZR’s mining contractor, is now fully mobilized at site with its equipment and operators.

Article content

The mining fleet is supporting the operation by moving material from active mining areas to the processing plant, providing a consistent supply of material for processing.

Article content

In parallel, JZR has worked to recruit and hire qualified operators and build an experienced operating team for the processing plant. Establishing this team has been an important part of the transition as the Company has assumed responsibility for day-to-day plant operations.

Article content

In August, the Company established a regular operating schedule consisting of one eight-hour shift per day, Monday through Friday. During this initial operating period, the team encountered several equipment failures and operational issues. These issues were addressed by the Company’s operating team, including repairs and the replacement of certain equipment components.

Article content

Story continues below

This advertisement has not loaded yet, but your article continues below.

Article content

The Company believes the operation has now stabilized and is focused on the next phase of the ramp-up. JZR is evaluating opportunities to increase operating hours, improve plant efficiency and increase the amount of material that can be consistently processed.

Article content

11 Tonnes of Concentrate Shipped

Article content

JZR is also pleased to report that approximately 11 tonnes of concentrate has been shipped from the Vila Nova Project and is currently in transit to São Paulo, with expected arrival on September 17, 2026.

Article content

The shipment represents an important operational milestone as JZR continues to integrate the mining and processing operations and advance the Project toward more consistent processing of material.

Article content

Robert Klenk, Chief Executive Officer of JZR Gold, commented:

Article content

“We are excited and encouraged by the progress that has been made. With the mining contractor now fully mobilized, material moving to the plant, an operating team in place and approximately 11 tonnes of concentrate now on its way to São Paulo, our focus is shifting toward increasing operating hours and improving efficiency. We believe this provides an important foundation for moving Vila Nova toward more consistent and sustained production.”