Mining Operations Underway and 11 Tonnes of Concentrate Shipped to São Paulo
Sign In or Create an Account
or View more offersArticle content
VANCOUVER, British Columbia, Sept. 15, 2026 (GLOBE NEWSWIRE) — JZR Gold Inc. (TSXV: JZR) (OTCPK: JZRIF) (the “Company” or “JZR”) is pleased to provide an operational update on the Vila Nova Gold Project (the “Project”) located in Amapá State, Brazil, following the Company’s assumption of operatorship on May 28, 2026.
Article contentWe apologize, but this video has failed to load.Try refreshing your browser, or
tap here to see other videos from our team.Article content
Since assuming operatorship, JZR has been focused on transitioning the Project into a stable and consistently operating processing operation. This transition has involved several important steps, including securing a mining contractor, mobilizing the necessary equipment to site, recruiting and training plant operators, and assembling an operating team capable of managing the Project.
Article content
Story continues below
This advertisement has not loaded yet, but your article continues below.
Article content
Mining Contractor Mobilized and Operations Established
Article contentArticle content
Following the assumption of operatorship, the Company required time to identify and secure an appropriate mining contractor, finalize a contract and mobilize the contractor and its equipment to the Project site. RR Bueno, JZR’s mining contractor, is now fully mobilized at site with its equipment and operators.
Article content
The mining fleet is supporting the operation by moving material from active mining areas to the processing plant, providing a consistent supply of material for processing.
Article content
In parallel, JZR has worked to recruit and hire qualified operators and build an experienced operating team for the processing plant. Establishing this team has been an important part of the transition as the Company has assumed responsibility for day-to-day plant operations.
Article content
In August, the Company established a regular operating schedule consisting of one eight-hour shift per day, Monday through Friday. During this initial operating period, the team encountered several equipment failures and operational issues. These issues were addressed by the Company’s operating team, including repairs and the replacement of certain equipment components.
Article content
Story continues below
This advertisement has not loaded yet, but your article continues below.
Article content
The Company believes the operation has now stabilized and is focused on the next phase of the ramp-up. JZR is evaluating opportunities to increase operating hours, improve plant efficiency and increase the amount of material that can be consistently processed.
Article content
11 Tonnes of Concentrate Shipped
Article content
JZR is also pleased to report that approximately 11 tonnes of concentrate has been shipped from the Vila Nova Project and is currently in transit to São Paulo, with expected arrival on September 17, 2026.
Article content
The shipment represents an important operational milestone as JZR continues to integrate the mining and processing operations and advance the Project toward more consistent processing of material.
Article content
Robert Klenk, Chief Executive Officer of JZR Gold, commented:
Article content
“We are excited and encouraged by the progress that has been made. With the mining contractor now fully mobilized, material moving to the plant, an operating team in place and approximately 11 tonnes of concentrate now on its way to São Paulo, our focus is shifting toward increasing operating hours and improving efficiency. We believe this provides an important foundation for moving Vila Nova toward more consistent and sustained production.”